NOC Conditions For Fresh Industry

Documents Withdrawal Less than 10 KLD Withdrawal between 10 to 100 KLD Withdrawal more than 100 KLD
Consent to Establish from State Pollution Control Board or letter from MoEF, or letter from State level Environmental Impact Assessment Authority or any other letter from statutory agencies indicating date of commencement of project (in case of OE area only). Yes Yes Yes
Affidavit on non-judicial stamp paper of Rs. 10/- by the applicant, confirming non/ inadequate availability of public water supply ( in case of water requirement is less than 10 KLD) OR Yes No No
Ground water quality report of existing ground water abstraction structure from NABL accredited/govt. approved lab No Yes Yes
Impact Assessment Report for OCS areas by accredited consultants (in case of water requirement is more than 100 KLD) No Yes Yes
Approval from Wetland Authority (in case of Project area falling within 500 meter of Wetland zone) Yes No No
Bharatkosh receipt for depositing Application Fee Yes Yes Yes
Affidavit regarding Non-availability of water supply from local government agencies Yes Yes Yes
Source Water Availability/Non-availability Certificate Yes No No
Ground Water Quality Report Yes Yes Yes
Aplication with Signature and Seal Yes Yes Yes